Original U.S. Department of Energy SealU.S. Department of Energy Office of History and Heritage Resources The Manhattan Project
An Interactive History



Y-12: Design, 1942-1943 ] Y-12: Construction, 1943 ] [ Y-12: Operation, 1943-1944 ] Working K-25 into the Mix, 1943-1944 ] The Navy and Thermal Diffusion, 1944 ]

Home
Events
People
Places
Science & Tech.
Special Topics
Resources

Back Next

Alpha Racetrack, Y-12 Electromagnetic Plant, Oak RidgeY-12: OPERATION
Oak Ridge: Clinton (1943-1944)
Events: The Uranium Path to the Bomb, 1942-1944

During the summer and fall of 1943, the Y-12 Electromagnetic Plant at Oak Ridge began to take shape.  The huge buildings to house the operating equipment were readied as manufacturers began delivering everything from electrical switches to motors, valves, and tanks.  While construction and outfitting proceeded, almost 5,000 operating and maintenance personnel were hired and trained.  Then, between October and mid-December, Y-12 paid the price for being a new technology that had not been put through its paces in a pilot plant.  Vacuum tanks in the first Alpha racetrackAlpha calutron operators at their control panels, Y-12, Oak Ridge. An overhead sign nearby reads "Do Not Visit With Cubicle Operators." leaked and shimmied out of line due to magnetic pressure, welds failed, electrical circuits malfunctioned, and operators made frequent mistakes.  Most seriously, the magnet coils shorted out because of rust and sediment in the cooling oil.  

Leslie Groves arrived on December 15 and shut the racetrack down.  The coils were sent to Allis-Chalmers with hope that they could be cleaned without being dismantled entirely, while measures were taken to prevent recurrence of the shorting problem.  The second Alpha track (Alpha 2, not to be confused with the Alpha II phase of the Y-12 Extension) now bore the weight of the electromagnetic effort.   In spite of precautions aimed at correcting the electrical and oil-related problems that had shut down the first racetrack, Alpha 2 fared little better when it started up in mid-January 1944.  While all tanks operated at least for short periods,Operator of an Alpha calutron control panel, Y-12, Oak Ridge. performance was sporadic and maintenance could not keep up with electrical failures and defective parts.  Like its predecessor, Alpha 2 was a maintenance nightmare.  

Alpha 2 produced about 200 grams of twelve-percent uranium-235 by the end of February, enough to send samples to Los Alamos for experimentation and feed the first Beta unit but not enough to satisfy estimates of weapon requirements.  The first four Alpha tracks did not operate together until April 1944, a full four months late.  While maintenance improved, output was well under previous expectations.  The opening of the Beta building on March 11 led to further disappointment.  Beam resolution was so unsatisfactory that complete redesign was required.  

Ernest Lawrence and others, nonetheless, remained convinced that Y-12 still offered the only realistic avenue to a bomb by 1945.  Despite his concernShift change at Y-12, Oak Ridge, August 1945. that the construction could not be completed in time, Groves therefore approved in May 1944 the construction of a third Beta building containing two racetracks.   Groves also agreed to a series of complicated changes in the racetracks that would allow their Alpha units to process the material originating from the gaseous diffusion plant, K-25.  This was necessary because K-25 had been experiencing even greater problems during 1943 and 1944 than Y-12.

 

Back Next

Click here to view sources and notes for this page.

 

Manhattan Project Home | History Office Home | DOE Home | Privacy and Security Notices
About this Site | How to Navigate this Site | Note on Sources | Site Map | Contact Us